8th Ave Pumprooms (MTA) Rehab. Pump Facilities Aug-04 Dec-05 $9,524,000.00
CAT-200 (Sub to JF White) Cat & Del Water Treat Sep-05 Oct-05 $119,579.00
Broadway Streetscapes Phase III Street & Sidewalk Jun-03 Nov-04 $4,188,188.00
No. Blvd.,Rte 25A,Nassau Asphalt Conc. Rehab  May -03 Sept -04 $2,598,794.00
MTA/TBTA Veranzano Bridge Fire Wire Lines Mar-03 Mar-04 $2,524,500.00
Edgemere Urban Renewal (DDC) Street/Sewer Reconstruction Dec-00 Oct-03 $13,434,349.00
Kensico Reservoir (DEP) Flow Control Mod May-01 Nov-05 $16,187,456.00
Enron/Ft. Hamilton Service Contract Service Contract May-01 Feb-02 $250,000.00
Rikers Island (EDC) Site Prep Oct-01 Feb-02 $1,868,750.00
St. George Ferry, Staten Island (TA) Rehab Tunnel Vent System Jul-99 Oct-01 $5,274,000.00
Battery Park Upper Promenade (DPR) Rehab Sep-00 Oct-01 $4,859,993.00
Whitehall Ferry (Sub. to Tishman-Harris) Excavation/Conc. Work Aug-01 Sep-01

T&M

65th St. Bridges/4Bridges (Queens)-DOT Rehab 4 Bridges Jan-00 May-01 $4,673,033.00
Fresh Kills, Staten Island (DOS) Gas/Odor Control Cond. May-99 May-01 $5,224,386.50
Van Cortlandt Park, Bx. (DEP) Sub. Sewer/Watermain Oct-00 Oct-00 $142,750.00
Coney Island, Bklyn. (Turner) Sub. Site Work Jun-00 Sep-01 $1,505,000.00
Stone St., Manhattan Street Reconstruction Nov-99 Jul-00 $1,812,655.25
Broadway Line, Manhattan (TA) Rehab. Pump Facilities Dec-95 Jun-00 $8,574,000.00
Emergency F.M. - 973-PS/Citywide Emergency Job Apr-97 Apr-99 $448,000.00
66th St. Station - TA Rehab. Dec-95 Mar-99 $12,100,000.00
Prospect Park, Brooklyn Rehab Apr-96 Aug-98 $2,500,000.00
Tennis Center/Queens (AFC/CAC) Site Work May-95 Jun-98 $11,600,000.00
Whitestone (AFC/CAC) Sewers May-98 May-98 $47,000.00
Greyhound Terminal (sub to Trataros) Site Work Mar-98 Mar-98 $25,000.00
Collapsed Sewers, Bx. /SEX-00201H Sewers Mar-97 Mar-98 $1,241,034.11
Fremont Ave., S.I. (DEP) Sewers Sep-97 Mar-98 $1,259,902.90
Prospect Park Sidewalks Repair May-97 Jan-98 $469,169.00
Pelham Line/Pump Facilities Mechanical Dec-93 Dec-97 $1,600,000.00
Rust St., Queens (DOT) Reconstruction Nov-96 Dec-97 $7,716,004.00
Sewers E. 124th St. (SEN-002127) Sewers Jul-97 Dec-97 $614,057.25
Outfall W. 21st St., Brooklyn Sewers Oct-96 Nov-97 $1,323,000.00
Heberton Ave. (DEP) Sewers Oct-96 Nov-97 $2,222,782.00
BPC Sea Wall Sea Wall Oct-96 Oct-97 $5,069,978.00
Baisley Blvd., Queens Highway Jan-97 Oct-97 $3,509,738.10
Church Ave. Sta. (Sub. to Beys) Utility Work Mar-97 Sep-97 $150,000.00
Woodhaven Blvd. (TA) Renovation Dec-93 Aug-97 $5,700,000.00
Elson St. - Sewers, S.I. (DEP) Sewers Aug-96 Aug-97 $1,424,633.75
Vernon Ave., Bklyn. (SEK-002246) Sewers Mar-97 Aug-97 $456,144.08
Powell's Cove Park/DPR Rehab. Park Jul-96 Jul-97 $3,022,385.00
Wales Ave./NYCDOT Bridge Jun-93 May-97 $5,600,000.00
65th Pl. Bridge/DOT Bridge Jul-95 Apr-97 $3,200,000.00
Surf Ave. - Bklyn. (DEP) Sewers Oct-96 Jan-97 $236,025.00
PR-62/Pt. Richmond/DEP (AFC/FCC) Gates/Actuators Mar-94 Dec-96 $785,394.00
Emergency Force Main - 849-PS Emergency Job Dec-94 Dec-96 $470,100.00
Reed Place - Bronx Sewers Jul-96 Dec-96 $380,000.00
Babbage St. - Q (DEP) Sewers Jul-96 Nov-96 $312,704.38
P.S. 88 - Queens Add./Alterations Sep-93 Aug-96 $16,400,000.00
Sewers 221st. St., Queens Sewers Jan-96 Aug-96 $741,024.00
LGA Paving (P.A.) Paving & Drainage Apr-96 Aug-96 $532,458.00
Canal St./PS-59 Pumping Station May-92 Jun-96 $1,600,000.00
Hillview Reservoir/Yonkers Flowmeter Apr-96 May-96 $79,500.00
WI-185 Man. & Bx./AFC/FCC Gate Operator/Grit May-94 Mar-96 $956,715.00
HP-169/DEP/Bronx Heat Pumps Feb-95 Jan-96 $260,000.00
Bridge Resurfacing, Bronx Resurface Jul-92 Oct-95 $1,800,000.00
North River WP-164 Wearing Course Sep-92 Oct-95 $3,900,000.00
L.I.E./D254225/NYSDOT Highway Sep-92 Oct-95 $19,500,000.00
Church Ave., Bklyn. Highway Jul-93 Oct-95 $4,800,000.00
Howard Beach/Rosedale P.S. Pumping Stations Nov-91 Sep-95 $11,000,000.00
Queens Criminal Court Ent. Add. Entrance/Renovation Dec-93 Sep-95 $5,400,000.00
Jamaica WPCP/J-118 Reconst. Tanks Apr-93 Aug-95 $290,950.00
WP-269/PS-14-22-B (AFC/FCC) P.S. & Force Main May-94 Aug-95 $3,200,000.00
Plunkett Ave. Sewers/WM May-93 Jul-95 $2,700,000.00
SE-689/110th Ave. (AFC/A&G) Sewers Nov-94 Jul-95 $1,100,000.00
E. 72nd St., Bklyn. Hwy./Sewer/WM Nov-94 Jul-95 $4,200,000.00
SC-61/Autumn Ave., Brooklyn Sewers/Dragging Mar-93 Jun-95 $1,000,000.00
St. Mary's Park Houses Sub. to Maric Piping Aug-94 Sep-94 $150,000.00
NC-109/Newtown Creek, Queens 4 Hyd. Cranes Feb-94 Jul-94 $137,196.00
Grinding - HW2CR94/DOT (Queens) Grinding Apr-94 Jul-94 $5,000,000.00
P.S. 50 - Queens Int. Rehab. May-92 May-94 $6,600,000.00
Warbasse Houses Piping Sep-92 May-94 $2,300,000.00
No. Conduit (SE-581) Sewer Jan-93 Apr-94 $3,200,000.00
SEQ-002326/49th St. Sewers Oct-93 Apr-94 $148,989.00
SEQ-200228/198th St. Sewers Nov-93 Apr-94 $290,987.70
Shore Rd., Bklyn. (DEP) Sewers Nov-93 Apr-94 $281,545.00
Jamaica Water Supply Emergency Job Dec-93 Feb-94 T&M
REG-18S Sluice Gates Mechanical Oct-91 Jan-94 $574,000.00
REG-18T Regulator Jan-92 Jan-94 $674,000.00
Hunter College Int. Renovation Aug-91 Dec-93 $2,900,000.00
Gun Hill Houses/NYCHA Mechanical Dec-92 Dec-93 $1,100,000.00
Rochdale Village, Queens Underground Piping Dec-92 Dec-93 $4,000,000.00
Bowery Bay/BB-114 (DEP) Sludge System Dec-92 Dec-93 $601,500.00
Arthur Kill Corr./SI Sanitary Sewer Jun-93 Dec-93 $42,836.00
Conner St. P.S., Bronx Pumping Station Dec-90 Nov-93 $9,100,000.00
Const. Sluice Gates  (NCB5 & NC6) Inst. Sluice Gate/REG-17H Jun-91 Nov-93 $525,000.00
Avenue "V" P.S. Pump Station Sep-91 Nov-93 $1,000,000.00
Jerome Park (62G) Corrosion Control Nov-91 Nov-93 $2,200,000.00
Woodmere P.S. (NCDPW) Pump Stations (3) Aug-91 Oct-93 $3,500,000.00
Croton Aqueduct (DEP) Structures Mar-93 Sep-93 $2,400,000.00
Sewers Beach 131 - 134th Sts. Sewers & WM Nov-91 Jul-93 $7,800,000.00
Bowery Bay/BB-92 Sludge Tank Apr-92 Apr-93 $139,977.00
Waterside Parkway/SI Sewers Oct-92 Apr-93 $357,234.00
WTC-169 Valve Replacement Valve Replacement Jan-92 Mar-93 $700,000.00
Jamaica WPCP/J-59 Sludge Tank Apr-92 Mar-93 $154,600.00
Resurf. 120th Ave., Queens Resurface Aug-92 Feb-93 $1,200,000.00
SEQ-002330/Hollywood Ave., Queens Sewers Oct-92 Feb-93 $373,781.00
Rikers Island (sub. w/Morse Diesel) Site Utility Jan-93 Feb-93 $1,900,000.00
Bullard Ave., Bronx Hwy. & Sewer Jan-91 Jan-93 $7,800,000.00
SEQ-002316 - 217th St. Sewers Sep-92 Jan-93 $56,941.00
SEQ-002315 - 192nd St. Sewers Sep-92 Jan-93 $127,723.00
SEQ-200196 - Queens Seepage & C.B. Jun-92 Dec-92 $563,045.00
Citywide Resurfacing/DOT/Grinding Prep. Highway Nov-91 Nov-92 $2,500,000.00
Brooklyn Villas Reconstruction Jul-92 Nov-92 $342,355.00
Recon. Collapsed Sewers/SEK00201S Sewers Sep-91 Sep-92 $860,227.00
Defective Sewers/SE-569I DEP Sewers Sep-91 Aug-92 $1,700,000.00
HWK 692TP (DOT), Bklyn. Subsurf. Invest. May-92 Aug-92 $158,153.00
South Cove (BPCA) Rep. Wood Quay Jun-92 Jul-92 $11,275.00
No. Esplanade WM & Site Jun-91 Jun-92 $1,700,000.00
Adams St., Bklyn./DGS Steam System Jan-92 May-92 $185,500.00
PO 42W - DEP San. Trailers Feb-92 Apr-92 $44,275.00
Tribeca Bridge/BPCA Pile Foundation Sep-91 Mar-92 $711,000.00
Corp. Kennedy Bridge Bridge Work Sep-90 Dec-91 $2,100,000.00
Betts Ave. Incin. HVAC Jul-91 Dec-91 $1,200,000.00
Hamilton Fish/NYCDPR Bldg. Renov. Feb-90 Nov-91 $8,300,000.00
Pedestrian Ramps (BPCA) Ramps May-91 Oct-91 $200,000.00
Tide Gates/Cadman Pl./REG 18B) Install Tide Gates Aug-91 Oct-91 $56,000.00
E. 91st St. Ramps/DOS Site Improve. Jul-91 Sep-91 $168,000.00
8th Ave. (Sub.) Sub. Hwy. Work Jun-89 Aug-91 $3,900,000.00
Defective Sewers/SE-569H Sewers/Rd. & Side. Mar-90 Aug-91 $2,000,000.00
Improve. Q-Midtown Tunnel/QMM-41 Vent. of Building Feb-91 Aug-91 $368,000.00
WI-157 - Grit Stage Area (WPCP) Staging Area Mar-91 Jul-91 $130,000.00
TI-80 - Grit Stage Area (Tallman Island) Grit Stage Mar-91 Jun-91 $145,000.00
Recon. Crames Sq./Bx. DOT Hwy./WM May-88 Jan-91 $5,000,000.00
College Pt. - Queens (Sub.) Sewers/WM Sep-89 Jan-91 $4,000,000.00
Rikers Island (Sub.) Water Main Dec-89 Dec-90 $7,000,000.00
Beach 137th St., Queens Sewers Feb-89 Oct-90 $8,300,000.00
Hollers/Throgs Neck Pumping Sta./DEP Mar-89 Oct-90 $8,100,000.00
Reconst. Kane St. P.S./Bklyn. NYSDOT/Pumping Sta. Feb-90 Oct-90 $2,400,000.00
Reg. Chamber 37 Ave., Queens DEP, Chamber Sep-90 Oct-90 $258,000.00
Watt Ave., Bronx Sewers May-90 Jun-90 $203,592.00
Granite Head CB, Bx. Catch Basins Nov-89 Apr-90 $1,200,000.00
Prince St., Queens PDC Hwy./Sewer Jul-88 Mar-90 $2,900,000.00
Cement Pipe/Design., Bklyn. DEP Sewer Work Oct-89 Mar-90 $6,500,000.00
QED-930 Test Pit & Borings/Queens Boring & Test Pits Feb-90 Mar-90 $480,000.00
Recon. Kew Gardens Rd. DOT Highways Sep-87 Dec-89 $3,900,000.00
REG-17A Amboy Rd./SI Plant Design Jul-89 Sep-89 $134,575.00
REG-17B Fisher Ave. Plant Design Aug-89 Sep-89 $97,765.00
123rd Ave., Queens DEP Sewer/Hwy. Jan-88 Aug-89 $9,500,000.00
Dwight St.., Bklyn. DEP Sewer Work Sep-88 Jun-89 $1,000,000.00